“This team (and individual) have delivered Moreton cutting (6xG switches on the main line between Didcot and reading) within the Easter block of 2015. This was after the Christmas fiasco so the scrutiny level was incredibly high. This was working with an unfamiliar signalling team and within the reading team’s possession.
All delivered successfully.
Then the Bat Hampton TPOD was recently successfully delivered during a 6 week block between Bath and Chippenham. This included 11 S&C units and 4700yds of PL. All track lowering under structures along the route. This has been dubbed the biggest project network rail has undertaken.“